Reliance letters in design and construction
Reports are often commissioned by parties involved in the design and construction of built assets that another party (other than the original client) then has to rely on to support or inform their own activities. Under such circumstances, the author of the report might issue a reliance letter, confirming that the third party can rely on the contents of the report, or can rely on a specific part of the report.
For example, an organisation selling a site might commission an assessment of geotechnical or environmental conditions that a purchaser later relies on when deciding whether to buy the site and at what price. Under these circumstances, the author of the report might issue a letter confirming that the purchaser can rely on the contents of the report.
Such a letter might include:
- A description of the report(s) to which the letter relates.
- The reason for the reliance.
- A warrant that the author exercised reasonable skill and care in preparing the report.
- Details of the original appointment agreement, perhaps limiting liability to that under the appointment (this requires that a copy of the appointment is provided).
- Other limitations to liability, such as a limiting period.
- A licence for use of the report.
- Confirmation of professional indemnity insurance.
- Consideration from the beneficiary to the consultant.
- A right to assign the benefit of the letter (for example to funders).
- Execution, perhaps as a deed.
This can be seen as a quicker and easier arrangement than providing a collateral warranty, or relying on the provisions of the Contracts (Rights of Third Parties) Act. However, it is important to ensure that the letter is carefully drafted and that the correct details are entered. Whether the result of a reliance letter is simply a common law duty to use reasonable skill and care, or whether it amounts to a contract between the parties that may introduce a greater duty will depend on the wording of the letter.
There are four essentials of a contract:
- Two or more parties; and
- An intention to create legal relations; and
- An agreement; and
- Consideration
The two essentials that might be disputed are an intention to create legal relations and consideration. This might be demonstrated by a consideration clause and by both parties executing the letter. However, even in the absence of such provisions, it may be apparent from the actions of the parties that the recipient of the letter has relied on it to their detriment, and this may be sufficient to establish ‘consideration’.
[edit] Related articles on Designing Buildings Wiki
- Assignment.
- Collateral warranty.
- Third party rights.
- Letter of intent.
- Letter of appointment.
- Essentials of a contract
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.





















Comments